June Site Update.

Christchurch's Winter weather means the latest set of drone photos below are a tad gloomy, but it certainly hasn't slowed down onsite progress. Simon Meggett, Civil Engineer from Davis Ogilvie & Partners provides this overview of recent siteworks at Factory Road Industrial Park:

  • Both the Northern and Western lots have been topsoiled and are now seeded at finished level.

  • The stormwater mains have been installed along roads two, three, and the majority of road one. Drainlayers are now working on the lateral connections for lots.

  • Roading has been cut to subgrade across the site and Road three has been built up with imported fill.

  • Stormwater management area has been completed and grassed.


The set of (rainy) drone images below were taken on Friday 21 June 2024: